QUESTION 87
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton
1. $1863/ton
2. $1948/ton D. $1836/ton
Answer: D
:
QUESTION 88
AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
1. Risk analysis
2. Benefit/Cost ratio (B/C) method
3. Net present worth method
4. Life cycle costs method (LCC)
Answer: D
:
QUESTION 89
can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.
1. Economic optimization
2. Simulation
3. Linear programming
4. Dynamic programming
Answer: D
:
QUESTION 90
What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?
1. Liability insurance
2. Performance bond
3. Bid bond
4. Surety bond
Answer: B
:
QUESTION 91
Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?
1. Productivity efficiency factor
2. Value engineering
3. Cash flow
4. The learning curve
Answer: D
:
QUESTION 92
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:
1. Precedence diagram method
2. Precedence and arrow diagram methods only
3. Gantt chart (bar chart) method
4. Arrow diagram method
Answer: B
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?
1. Project will be completed in 20 more weeks
2. Project will be completed this week - on schedule
3. Project will be completed in 4 more weeks
4. Project will be completed in 12.8 more weeks
Answer: C
:
QUESTION 94
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
1. Recalculate the early finish for each activity
2. Recalculate the early start for each activity
3. Update the remaining duration for each activity
4. Recalculate the critical path
Answer: D
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The recognition of loss of value of a natural resource used in the production process is referred to as:
1. Capital reduction
2. Net loss
3. Depreciation
4. Depletion
Answer: D
:
User: Maksim*****![]() ![]() ![]() ![]() ![]() The study materials provided by killexams.com cover all aspects of the CCE-CCC exam, making it a must-have for anyone new to it. Thanks to killexams.com, I was able to increase my expertise in CCE-CCC and have recommended it to my friends and colleagues. Even on the day before my CCE-CCC exam, when I usually went for a run to feel energized, I turned to killexams.com for educational materials to help me prepare. |
User: Doreen*****![]() ![]() ![]() ![]() ![]() I had limited time to prepare for the cce-ccc exam and needed a clear and effective guide urgently. After an extensive search, I discovered the questions and answers provided by Killexams.com, which made my day. The short and pointed answers helped me grasp the topics quickly, and I was able to secure excellent marks in the exam. The material was also easy to memorize, and I am impressed and satisfied with my outcome. |
User: Taska*****![]() ![]() ![]() ![]() ![]() I passed the CCE-CCC exam this month with the help of killexams.com very reliable preparation questions and answers. I did not think that practice tests could help me achieve such high marks, but now I know that killexams.com is more than just a practice test. It provides you with everything you need to pass the exam and learn everything you need to know, saving your time and effort. |
User: Elsie*****![]() ![]() ![]() ![]() ![]() I searched online for the perfect practice test for this unique subject matter but could not find an appropriate one that explained the critical concepts needed. However, when I discovered Killexams.com brain practice test material, I was truly amazed. It included all essential topics without being overwhelming. I am thrilled to have found and used it. |
User: Stasya*****![]() ![]() ![]() ![]() ![]() I wholeheartedly recommend killexams.com to anyone who wants to excel in the CCE-CCC exam. Their study guide helped me score an 89%, and I was extremely pleased with the results. I realized that extensive memorization was not the only solution to success in exams after using the killexams.com practice tests to prepare for my CCE-CCC exam. I am incredibly satisfied with my performance. |
Features of iPass4sure CCE-CCC Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux