PMI CCE-CCC Questions & Answers

Full Version: 95 Q&A


Latest CCE-CCC Exam Questions and Practice Tests 2025 - Killexams.com


CCE-CCC Dumps CCE-CCC Braindumps

CCE-CCC Real Questions CCE-CCC Practice Test CCE-CCC Actual Questions


killexams.com


PMI


CCE-CCC


Certified Cost Consultant / Cost Engineer (AACE International)


https://killexams.com/pass4sure/exam-detail/CCE-CCC


:


QUESTION 87


The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton

  1. $1863/ton

  2. $1948/ton D. $1836/ton


Answer: D


:


QUESTION 88

AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.


  1. Risk analysis

  2. Benefit/Cost ratio (B/C) method

  3. Net present worth method

  4. Life cycle costs method (LCC)


Answer: D


:


QUESTION 89

can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.


  1. Economic optimization

  2. Simulation

  3. Linear programming

  4. Dynamic programming


Answer: D


:


QUESTION 90

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?


  1. Liability insurance

  2. Performance bond

  3. Bid bond

  4. Surety bond


Answer: B


:


QUESTION 91

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?


  1. Productivity efficiency factor

  2. Value engineering

  3. Cash flow

  4. The learning curve


Answer: D


:


QUESTION 92

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:


  1. Precedence diagram method

  2. Precedence and arrow diagram methods only

  3. Gantt chart (bar chart) method

  4. Arrow diagram method


Answer: B


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?


  1. Project will be completed in 20 more weeks

  2. Project will be completed this week - on schedule

  3. Project will be completed in 4 more weeks

  4. Project will be completed in 12.8 more weeks


Answer: C


:


QUESTION 94

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?


  1. Recalculate the early finish for each activity

  2. Recalculate the early start for each activity

  3. Update the remaining duration for each activity

  4. Recalculate the critical path


Answer: D


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The recognition of loss of value of a natural resource used in the production process is referred to as:


  1. Capital reduction

  2. Net loss

  3. Depreciation

  4. Depletion


Answer: D


:


User: Mitre*****

Before using killexams.com, I thought I could pass the CCE-CCC exam without much preparation. However, after using their Questions and Answers material, I realized that it had given me the necessary knowledge to pass the exam with 90%. The material is well-designed, effective, and dependable. I thank killexams.com for providing me with dynamic material for my mastering of the CCE-CCC exam.
User: Nata*****

Without killexams.com, I am confident that I would not have been able to pass the CCE-CCC exam. Their Questions and Answers material was simply astonishing, and it gave me the required knowledge to ace the exam. I am elated to have scored 92%, a personal best for me. The material is well-organized, effective, and dependable, making it the perfect tool for success.
User: Lukah*****

I struggled during my preparation for the PMI CCE-CCC exam and sought help from friends, but the material they provided was confusing. Later, I found Killexams.com and their Questions and Answers material. The treasure trove of information helped me understand everything from top to bottom, and I answered all the questions with perfect options. Thank you for bringing endless happiness to my profession.
User: Slavik*****

Thanks to the killexams.com kit, I took the CCE-CCC exam last month and passed it. It is an outstanding exam practice test, more reliable than I could have anticipated. All questions are valid, and it provides a wealth of practice information. I passed with over 97%, which is an excellent CCE-CCC exam score. I will be spreading the word among my friends because Killexams is outstanding and can be beneficial to many.
User: Oliver*****

The Killexams.com questions and answers made me feel confident enough to tackle the CCE-CCC exam. I was able to answer 90 out of 95 questions in due time and passed effectively, something I never thought possible before. Their reliable exam preparation and complete content made me notably occupied, and I came to appreciate Killexams.com and their incredible service.

Features of iPass4sure CCE-CCC Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list