Question #274 Section 6
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
8
18
36
40
Answer: C Reference:
https://www.izenbridge.com/blog/how-to-calculate-communication-channels/
Question #275 Section 6
A project conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type communication is this?
Informal
Unofficial
Formal
Hierarchical
Answer: A Reference:
https://yodiz.com/help/agile-scrum-meetings/
Question #276 Section 6
Which of the following are processes associated with Project Cost Management?
Develop Costs, Estimate Costs, Determine Budget, Control Costs
Develop Budget, Determine Budget, Determine Risks, Control Costs
Plan Cost Management, Estimate Costs, Determine Budget, Control Costs
Plan Budget Management, Determine Budget, Create Cost Accounts, Control Costs
Answer: C Reference:
https://blog.masterofproject.com/cost-management/
Question #277 Section 6
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated.
Which estimation method did the team use?
Rolling wave planning
Expert judgment
Decomposition
Data analysis
Answer: C
Question #278 Section 6
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
Project level
Organizational level
Industry level
Influential level
Answer: C
Question #279 Section 6
A project had four phases, and at the end of the third phase, the project manager realized that some of the project execution steps could have been improved to avoid team burn out
What should the project manager have done differently?
Conduct performance reviews
Review quality reports with the project team
Hold regular meetings with the project team
Conduct a retrospective session at the end of each phase
Answer: D
Question #280 Section 6
A project manager is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?
Monitor Stakeholder Engagement
Monitor Communications
Manage Communications
Manage Stakeholder Engagement
Answer: D Reference:
https://www.memrise.com/course/352178/pmbok-5-project-management-exam-study/52/
Question #281 Section 6
Stakeholder identification and engagement should begin during what phrase of the project?
After the project management is completed
After the stakeholder engagement plan is completed
As soon as the project charter has been approved
After the communications management plan is completed
Answer: C Reference:
https://pmstudycircle.com/2012/06/identify-stakeholders-project-management/
Question #282 Section 6
What type of risk is Variability risk?
Emerging risk
Non-event risk
Ambiguity risk
Integrated risk
Answer: D
Question #283 Section 6
A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project manager's sphere of influence does this represent?
The project
The organization
Professional discipline
Across disciplines
Answer: C
Question #284 Section 6
What is the main benefit of the lessons learned register?
Provides validation requirements
Supplies monitoring and reporting methods
Improves the performance of future projects
Documents the status of deliverables and project results
Answer: C
Question #285 Section 6
What major skill sets comprise the PMI Talent Triangle?
Technical project management, technology management, and strategic and business management
Technical project management, leadership, and strategic and business management
Leadership, operational management, and technical project management
Organizational management, operational management, and technology management
Answer: B Reference:
https://www.pmi.org/learning/training-development/talent-triangle#:~:text=The%20ideal%20skill%20set%20%E2%80%94%20the,%E2%80%94% 20and%20now%2C%20digital%20skills
.
Question #286 Section 6
What tool or technique will establish expected behaviors for project team members?
Ground rules
Decision making
Power/influence grid
Stakeholder engagement assessment matrix
Answer: A
User: Martin Hoax*****![]() ![]() ![]() ![]() ![]() After trying a few practice tests, I finally settled on Killexams.com practice tests. The precise answers were delivered in a simple manner that was exactly what I needed. With only 10 days left until my CAPM exam, I was struggling with the subjects and feared that I would not pass. However, I managed to pass with a score of 78%, thanks to their study materials. |
User: Luciana*****![]() ![]() ![]() ![]() ![]() Initially concerned about an outdated CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (CAPM) - 2025 practice test, I contacted10:54 AM +03 on Wednesday, May 28, 2025, contacted killexams.com’s support team and learned their materials were fully updated. Their efficient customer service and high-quality Questions and Answers gave me confidence, and I am excited to take my CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (CAPM) - 2025 exam in two weeks, knowing I am well-prepared. |
User: Ishaan*****![]() ![]() ![]() ![]() ![]() I recently renewed my killexams.com membership for the CAPM exam, finding their tests essential for my preparation. The high-quality practice tests give me confidence that I will score over 95%. I am grateful for their outstanding resources and encourage others to use them. |
User: Masha*****![]() ![]() ![]() ![]() ![]() My name is Suman Kumar, and I scored 89.25% on the capm exam using Killexams.com’s test materials. Their detailed answer explanations and unique question bank made complex calculations and concepts much clearer. This resource was invaluable to my success. |
User: Gertrude*****![]() ![]() ![]() ![]() ![]() I am proud to have passed my PMI exams with an 84% score, thanks to killexams.com’s effective practice tests and software. The concise answers clarified complex subjects, making my preparation manageable despite a tight schedule. I am grateful for their reliable materials and recommend them to anyone seeking a straightforward path to certification success. |
Features of iPass4sure CAPM Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 1102 Q&A
Get Full VersionAll PMI Exams
PMI ExamsCertification and Entry Test Exams
Complete exam list