Question: 59
Participating in PI planning enables teams to gain alignment and commitment around a clear set of what?
team dependencies
prioritized objectives
user stories
r: B
on: 60
an anti-pattern to motivation? imizing purpose
vidualized compensation ket disruption
Team goals
r: B ation:
www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/
on: 61
siness must depend on the team for what in order for the business to do any meaningful planning? oss-functional skill set
mitment to the plan surements
capabilities
Answe
Questi
What is
Max
Indi
Mar D.
Answe Explan https://
Questi
The bu
a cr
com
mea
team
Answer: C
Question: 62
When does the plan-do-check-adjust cycle occur in scrum?
at the iteration review
in the daily scrum
at all formal scrum events
as part of the iteration retrospective
Answer: C
Question: 63
What are the three pillars of Scrum?
Agility
Transparency
inspection
adaptation
r: B, C, D
on: 64
ing the goals of Release on Demand requires an understanding of how to decouple what? elease from deployment
terations Demos ystem Demos roject Increment
r: A ation:
www.scaledagileframework.com/continuous-deployment/
on: 65
oaches do not give people the answer, but instead they do what? hold them to their commitments
make the decisions
guide people to the solution limit the number of questions
Answe
Questi
Achiev
The r
The I
The S
The P
Answe Explan https://
Questi
Good c
They
They
They
they
Answer: D
Question: 66
At the System Demo, each team demonstrates their own work but the system is not integrated. They say they underestimated the integration effort, but they cannot integrate every Iteration and meet the planned scope.
What should the Scrum Master suggest?
Integrate the system during the IP Iteration
Stop the Train and go back to waterfall until integration can occur
Defer integration until the train is in the sustain and improve the section of the Implementation Roadmap
Discuss removing scope with product management to allow for continuous integratio
Answer: C Explanation:
https://www.scaledagileframework.com/system-demo/
Question: 67
rovide regular, predictable dev cadence to produce an increment of value ive the ART members a process tool to keep the train on the tracks
reate a continuous flow of work to support the delivery pipeline
llow the team to perform some final backlog refinement for upcoming iteration planning
r: A
on: 68
velopment Team may need to learn or acquire new skills. Where is this list of skills found? art of the outcome of the PI Planning pre-meeting
the Improvement Roadmap
art of the outcome of the Team Retrospective he HR Training and Development Plan
r: C ation:
www.scaledagileframework.com/dev-team/
on: 69
PI planning, which two tasks are part of the scrum master’s role in the first team breakout? vide clarifications necessary to assist the team with their story estimating and sequencing
ew and prioritize the team backlog as part of the preparatory work for the second team breakout
What is the purpose of the plan-do-check-adjust cycle?
To p
To g
To c
To a
Answe
Questi
The De
As p
In
As p
In t
Answe Explan https://
Questi
During
Pro
revi
Be involved in the program backlog refinement and preparation
identify as many risks and dependencies as possible for the management review
facilitate the coordination with other teams for dependencies
Answer: A, E
Question: 70
What are two common PI planning anti-patterns?
Too much time spent analyzing each story
Too much time spent prioritizing features
Team decides which changes need to happen and when
Part-time scrum masters do not have time to plan as part of the team
Stories are created for the PI planning iterations
Answer: A, D
Features of iPass4sure SSM Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 70 Q&A
Get Full VersionAll SAFe Exams
SAFe ExamsCertification and Entry Test Exams
Complete exam list