PMI PMI-RMP Questions & Answers

Full Version: 443 Q&A


Latest PMI-RMP Exam Questions and Practice Tests 2025 - Killexams.com


PMI-RMP Dumps

PMI-RMP Braindumps PMI-RMP Real Questions PMI-RMP Practice Test

PMI-RMP Actual Questions


PMI


PMI-RMP


PMI Risk Management Professional


https://killexams.com/pass4sure/exam-detail/PMI-RMP


Question #428


In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?


  • Evaluate the results of the Monte Carlo analysis.

    Document and periodically update project risk information

    Monitor project metrics and performance information.

    Update the risk management plan.


  • Answer: C Question #429

    How can the project manager rank competing stakeholder priorities for all the identified risks?


  • Perform qualitative and quantitative risk analysis.

    Engage the project sponsor to decide.

    Refer to stakeholder analysis prioritization tree.

    Perform a review of organizational process assets.


  • Answer: A Question #430

    A project team is conducting initial risk planning. What other risk-related task should the project manager perform?


  • Identifying the risk threshold

    Determining the risk register headings

    Scoring the risks utilizing the risk matrix

    Prioritizing the risks in the risk register


  • Answer: A Question #431

    What are the critical success factors for the Plan Risk Management process?


  • Mitigate all risks, engage stakeholders, and follow organizational policies.

    Identify and address barriers, engage stakeholders, and follow organizational policies.

    Contingency reserves engage stakeholders and follow organizational policies.

    Identify and address barriers, engage stakeholders, and follow government regulations.


  • Answer: B Question #432

    A project team's risk facilitator identifies a number of risks and must prioritize them based on the organization's risk appetite levels. Which technique should be used?


  • PERT

    Stakeholder risk profile analysis

  • Project scope statement analysis

    Monte Carlo technique


  • Answer: B Question #433

    A risk manager wants to determine which risks are going to have the highest impact on a project. Which of the following techniques should the risk manager use?


  • Assumptions analysis

    Sensitivity analysis

    Root cause analysis

    Prioritization matrices


  • Answer: D Question #434

    The project manager wants risk metrics established for the new project. Which of the following metrics listed is best suited for this purpose?


  • Effectiveness of the work breakdown structure

    Number of approved project change requests

    Number of detects identified

    Effectiveness of response plans


  • Answer: D Question #435

    Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?


  • Develop risk responses, create risk management plan, and stay alert for risk events.

    Update the lessons learned documents, develop risk responses, and create the risk management plan.

    Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.

    Review lessons learned document to identify risks, quantity risks, and lower impact ratings.


  • Answer: C Question #436

    A cost analyst team member asks the project manager for the latest risk data for inclusion with the cost estimates for the project. Which tool should the cost analyst team member use to identify the probability of achieving specific cost targets?


  • Monte Carlo analysis

    Decision tree analysis

    Analogous estimating

    Brainstorming


  • Answer: A Question #437

    Most risks are assessed for probability and impact. Which of the following are other factors that should be considered?


  • Urgency and complexity

    Manageability and cost

    Urgency and manageability

    Manageability and complexity


  • Answer: C Question #438

    A pharmaceutical company undertakes a new, year-long research and development (R&D) project. The company pursues high margins on investments and an aggressive growth strategy. They maintain a central program management office (PMO) to assist with new projects and record data on past project performance.

    The company leadership regularly makes decisions regarding the full suite of company projects and requires comparative data and reports. Project leadership is well-versed in risk management and the PMO requires full documentation of project management artifacts.

    Based on the characteristics of this new project, which of the following best describes the risk strategy for the project?


  • Low stakeholder risk appetite, leverage historical project planning data, develop standard metrics and reports, and develop a formal risk management plan.

    High stakeholder risk appetite; leverage historical project planning data, develop standard metrics and reports, develop a formal risk management plan.

    High stakeholder risk appetite; leverage historical project planning data, utilize informal metrics and reports, develop risk management training.

    Low stakeholder risk appetite; collect new project data, create custom metrics and reports, and develop a formal risk management plan.


  • Answer: B Question #439

    Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?


  • Government regulations, industry best practice templates, organizational standard processes, and competitor landscape

    Government regulations, industry standards, conditions of the marketplace, and competitor landscape

    Government regulations, risk categories, organizational standard processes, and competitor landscape

    Government regulations, human resource policies and procedures, organizational standard processes, and competitor landscape


  • Answer: B Question #440

    A project manager is leading a project review meeting with the risk manager and the other project stakeholders. Which of the following are typical risk-related agenda items for a project review meeting?


  • Enterprise environmental factors and the risk register

    Risks closed in the last period and the risk appetite of the organization

    Organizational process assets and the risk register

    Risks closed in the last period and the trigger conditions that have occurred


  • Answer: D Question #441

    As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders. Which of the following inputs are used to identify project stakeholders?


  • Project charter, management reserve, enterprise environmental factors, and organizational process assets

    Project management plan, human resource plan, enterprise environmental factors, and organizational process assets

    Project charter, bid documents, enterprise environmental factors, and organizational process assets

    Project charter, communications management plan, enterprise environmental factors, and organizational process assets

  • Answer: C Question #442

    The project manager receives an updated project schedule from a sub team detailing the deliverables, dates, and durations for a critical milestone on the development and testing for offshore activities. This report is received one hour before a meeting with the chief executive officer (CEO) to present an updated master schedule of the critical path. The CEO has been promised a discussion on the project schedule several times. However, based on the recent update from the off-shore team, the project manager realizes this new schedule is not realistic. There are new risks associated with it and it is not well thought out. Some key stakeholders want to present this revised plan to the CEO. This meeting has been postponed twice already.

    Which action should the project manager take before meeting with the CEO?


  • Talk to the stakeholders before the meeting to discuss the options and ask their opinion.

    Present the revised master schedule to the CEO with the caveat that its being updated as new information is received, and these are the current dates at this point.

    Request the meeting be re-scheduled before presenting the master schedule to the CEO, stating that new major risks were identified and need to be assessed thoroughly.

    Present the revised schedule to the CEO and only answer questions about validity, if asked.


  • Answer: A Question #443

    Which of the following are examples of relevant data gathering tools?


  • Risk response plan and interviews

    Questionnaires and historical data

    Work breakdown structure an historical data

    Work breakdown structure and interviews


  • Answer: B


    User: Olyssia*****

    Due to the abundance of tiny details and configuration tricks required for the PMI-RMP exam, Killexams.com proved to be a blessing for me, even though I had little experience with the topic. Their PMI-RMP questions and answers were sufficient to sit and pass the exam.
    User: Henry*****

    I had taken the PMI-RMP arrangement from Killexams.com as it provided me with a medium-level preparation that had given me the notable degree of planning to achieve the 92% score in the PMI-RMP exam test. The tool helped me with the subjects in an interesting way, and I was able to get through them with ease. It made my preparation much less complex, and with the help of Killexams.com, I was organized enough to do well in the exam.
    User: Ibrahim*****

    As an IT professional, my skills and knowledge need to be top-notch. However, with a busy job and many responsibilities, I found it challenging to make time for thorough preparation. Thats when I discovered the well-organized questions and answers guide provided by killexams.com practice tests, which helped me achieve the right score within the stipulated time in pmi-rmp.
    User: Sashenka*****

    I am delighted that I purchased the pmi-rmp exam practice tests from killexams.com. The exam is difficult as it covers a vast range of topics. However, killexams.com covered everything perfectly, and there were tons of related questions about the exam.
    User: Renata*****

    I achieved a score of 89.1% on the PMI-RMP exam thanks to the excellent test material provided by Killexams. The questions were clear, concise, and covered the entire material thoroughly. The arrangement of the questions was also helpful in preparing for the exam. I am grateful to the Killexams team for their exceptional support.

    Features of iPass4sure PMI-RMP Exam

    • Files: PDF / Test Engine
    • Premium Access
    • Online Test Engine
    • Instant download Access
    • Comprehensive Q&A
    • Success Rate
    • Real Questions
    • Updated Regularly
    • Portable Files
    • Unlimited Download
    • 100% Secured
    • Confidentiality: 100%
    • Success Guarantee: 100%
    • Any Hidden Cost: $0.00
    • Auto Recharge: No
    • Updates Intimation: by Email
    • Technical Support: Free
    • PDF Compatibility: Windows, Android, iOS, Linux
    • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

    All PMI Exams

    PMI Exams

    Certification and Entry Test Exams

    Complete exam list