Answer: C


QUESTION: 134

When are acceptance tests typically written for a user story?


  1. After coding the story, but before user acceptance testing begins

  2. After writing the story, but before coding begins

  3. At the start of Product Backlog prioritization planning

  4. After estimating the Product Backlog, but before Sprint planning begins


Answer: C


QUESTION: 135

Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?


  1. Fast-Flexible-Flow

  2. Optimize the Whole

  3. Deliver Early and Often

  4. Eliminate Waste


Answer: D


QUESTION: 136

What do project reports show during the Sprint review meeting?


  1. Estimates compared to the baseline

  2. Actual results to the plan

  3. Return on investment (ROI)

  4. Earned value measurement (EVM)


Answer: C


QUESTION: 137

The purpose of "setting the stage'' in a project retrospective is to:


  1. Restate the goal of the meeting and create an open atmosphere.

  2. Review the scope statement and summarize project results.

  3. Elevate the team's morale and ensure that everyone participates.

  4. Describe the next Iteration and discuss lessons learned.


Answer: A


QUESTION: 138

A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called:


  1. Story

  2. Timebox

  3. Iteration

  4. Burndown


Answer: C


QUESTION: 139

When facilitated and managed well, the primary benefits of a project retrospective should be to:


  1. Increase empowerment and enjoyment for the team.

  2. Identify the most important issues for the sponsors.

  3. Provide an open forum for team member complaints.

  4. Allow the team to get ahead on release planning.


Answer: D


QUESTION: 140

In a Lean project environment, visual controls:


  1. Can be used by management for communicating specific corrective direction.

  2. Are easy to use, reflect the team's progress, and show the team what to do next.

  3. Are helpful while the team is forming but are less important for more experienced teams.

  4. Should be kept to a minimum to avoid distracting the team from high-value activities.


Answer: A


QUESTION: 141

Which term best describes an Agile project's approach to risk analysis?


  1. Regression

  2. Pareto

  3. Qualitative

  4. Monte Carlo


Answer: D


QUESTION: 142

The primary purpose of a Sprint retrospective is for the team to:


  1. Review stories planned for the next sprint and provide estimates,

  2. Demonstrate completed user stories to the Product Owner.

  3. Discuss what went well, what didn't, and ways to improve.

  4. Individually provide status updates on user stories in progress.


Answer: C


QUESTION: 143

In a Lean Software Development environment, the Project Leader strives to eliminate:


  1. Work in Process (WIP) and bugs.

  2. Delays and building what is not needed.

  3. Defects and features with low value stream values.

  4. Poor requirements and changing scope.


Answer: C


QUESTION: 144

During iteration planning, the team is discussing the design for a user story. A team member states that a design document should be started since the system is complex in nature. Another team member responds that in Agile there is no documentation. How should the ScrumMaster respond?


  1. Agree that documentation should be avoided, since it slows the progress of the team.

  2. Explain that interactions are valued over documentation, but documentation is not forbidden.

  3. Ask the manager if the technical processes mandate that designs be documented.

  4. Ask the Product Owner if it is acceptable for the resources to spend time on documentation.


Answer: B


QUESTION: 145

For a "caves and commonroom arrangement, the most appropriate prerequisite is that the people in the room must be working on:


  1. Whatever they choose.

  2. Individual projects.

  3. The same set of multiple projects,

  4. The same project.


Answer: D


User: Kirill*****

I am pleased to see that the PMI-200 brain dump test is up to date, and the recent modifications are hard to find elsewhere. Since I took my first PMI-200 exam, I am now preparing for the next step, and I plan to order soon.
User: Gaston*****

Do you feel that sweet sense of victory? I sure do, and it is a pleasant feeling. If you want to experience the same, head over to killexams.com to prepare for your PMI-200 exam. I did just that and was thrilled with the quality of the practice tests provided. The facilities offered by killexams.com are perfect, and there is no need to worry about failing. I passed the exam with flying colors, and so can you!
User: Tanita*****

Clearing the pmi-200 exam seemed unrealistic to me at first because the test factors were honestly extreme. However, the Killexams.com exam guide illuminated my shortcomings, and I was able to correctly answer 90 out of 100 questions. The top-notch exam simulator helped me pass the pmi-200 exam with ease. I offer my gratitude to Killexams.com for providing these wonderful services.
User: Nadya*****

I was struggling to pass the pmi-200 exam, but killexams.com made it easy with their language and concise features. With their practice tests, I was able to wrap up my training in just three weeks and pass the exam with an impressive score of 88%. The questions and answers provided were remarkable, and I appreciate killexams.com for their excellent work.
User: Mathias*****

I am thrilled to have obtained certification in Test pmi-200 with the help of Killexams. The excellent layout of the latest modules made it possible for me to attempt all 38 questions within the given timeframe, resulting in a score of more than 87%. I must say that I could not have done it without killexams.com Questions and Answers, which provide cutting-edge questions and cover all related topics.

Features of iPass4sure PMI-200 Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list