PMI PMI-200 Questions & Answers

Full Version: 145 Q&A


Latest PMI-200 Exam Questions and Practice Tests 2025 - Killexams.com


PMI-200 Dumps

PMI-200 Braindumps PMI-200 Real Questions PMI-200 Practice Test

PMI-200 Actual Questions


PMI


PMI-200


PMI-Agile Certified Practitioner (PMI-ACP)


https://killexams.com/pass4sure/exam-detail/PMI-200


Answer: C


QUESTION: 134

When are acceptance tests typically written for a user story?


  1. After coding the story, but before user acceptance testing begins

  2. After writing the story, but before coding begins

  3. At the start of Product Backlog prioritization planning

  4. After estimating the Product Backlog, but before Sprint planning begins


Answer: C


QUESTION: 135

Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?


  1. Fast-Flexible-Flow

  2. Optimize the Whole

  3. Deliver Early and Often

  4. Eliminate Waste


Answer: D


QUESTION: 136

What do project reports show during the Sprint review meeting?


  1. Estimates compared to the baseline

  2. Actual results to the plan

  3. Return on investment (ROI)

  4. Earned value measurement (EVM)


Answer: C


QUESTION: 137

The purpose of "setting the stage'' in a project retrospective is to:


  1. Restate the goal of the meeting and create an open atmosphere.

  2. Review the scope statement and summarize project results.

  3. Elevate the team's morale and ensure that everyone participates.

  4. Describe the next Iteration and discuss lessons learned.


Answer: A


QUESTION: 138

A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called:


  1. Story

  2. Timebox

  3. Iteration

  4. Burndown


Answer: C


QUESTION: 139

When facilitated and managed well, the primary benefits of a project retrospective should be to:


  1. Increase empowerment and enjoyment for the team.

  2. Identify the most important issues for the sponsors.

  3. Provide an open forum for team member complaints.

  4. Allow the team to get ahead on release planning.


Answer: D


QUESTION: 140

In a Lean project environment, visual controls:


  1. Can be used by management for communicating specific corrective direction.

  2. Are easy to use, reflect the team's progress, and show the team what to do next.

  3. Are helpful while the team is forming but are less important for more experienced teams.

  4. Should be kept to a minimum to avoid distracting the team from high-value activities.


Answer: A


QUESTION: 141

Which term best describes an Agile project's approach to risk analysis?


  1. Regression

  2. Pareto

  3. Qualitative

  4. Monte Carlo


Answer: D


QUESTION: 142

The primary purpose of a Sprint retrospective is for the team to:


  1. Review stories planned for the next sprint and provide estimates,

  2. Demonstrate completed user stories to the Product Owner.

  3. Discuss what went well, what didn't, and ways to improve.

  4. Individually provide status updates on user stories in progress.


Answer: C


QUESTION: 143

In a Lean Software Development environment, the Project Leader strives to eliminate:


  1. Work in Process (WIP) and bugs.

  2. Delays and building what is not needed.

  3. Defects and features with low value stream values.

  4. Poor requirements and changing scope.


Answer: C


QUESTION: 144

During iteration planning, the team is discussing the design for a user story. A team member states that a design document should be started since the system is complex in nature. Another team member responds that in Agile there is no documentation. How should the ScrumMaster respond?


  1. Agree that documentation should be avoided, since it slows the progress of the team.

  2. Explain that interactions are valued over documentation, but documentation is not forbidden.

  3. Ask the manager if the technical processes mandate that designs be documented.

  4. Ask the Product Owner if it is acceptable for the resources to spend time on documentation.


Answer: B


QUESTION: 145

For a "caves and commonroom arrangement, the most appropriate prerequisite is that the people in the room must be working on:


  1. Whatever they choose.

  2. Individual projects.

  3. The same set of multiple projects,

  4. The same project.


Answer: D


User: Irene*****

Passing the pmi-200 exam with a 92% score was a moment of great pride, thanks to the outstanding study resources from Killexams.com. Their test prep materials simplified the preparation process significantly, making complex topics easy to grasp. The course notes and exam simulator provided me with the confidence and skills needed to excel, particularly in areas like trainer communication and presentation techniques. I highly commend their efforts and encourage them to continue their excellent work.
User: Kliment*****

PMI-200 practice test was incredibly useful. Every question and answer was accurate, helping me pass with flying colors last week.
User: Rubal*****

Balancing a full-time job with pmi-200 exam preparation was challenging, but killexams.com’s reliable testprep materials made it manageable. I answered 90 out of 95 questions correctly and passed the exam, a feat I never thought possible. Discovering their resources while searching for study materials was a game-changer.
User: Vitaliy*****

Preparing for the PMI-200 exam was tough, but Killexams.com’s PMI test coaching materials made it manageable. Their resources were incredibly helpful, and I passed with confidence.
User: Stasha*****

The pressure to pass my pmi-200 exam to maintain my position at work was overwhelming, but killexams.com’s testprep and exam simulator made the process manageable. Their well-organized questions and answers allowed me to memorize key concepts efficiently, and the simulator mirrored the real exam experience. I am proud to say I am now pmi-200 certified, and I owe my success to killexams.com’s outstanding support.

Features of iPass4sure PMI-200 Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list