PMI PMI-100 Questions & Answers

Full Version: 704 Q&A


Latest PMI-100 Exam Questions and Practice Tests 2025 - Killexams.com


PMI-100 Dumps

PMI-100 Braindumps PMI-100 Real Questions PMI-100 Practice Test

PMI-100 Actual Questions


PMI


PMI-100


Certified Associate in Project


https://killexams.com/pass4sure/exam-detail/PMI-100


QUESTION: 345

When cost variance is negative and schedule variance is positive, the project is:


  1. under budget and behind schedule.

  2. over budget and ahead of schedule.

  3. on schedule.

  4. complete; all planned values have been earned.


Answer: B


QUESTION: 346

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?


  1. Reserve analysis

  2. Three-point estimating

  3. Parametric estimating

  4. Analogous estimating


Answer: D


QUESTION: 347

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:


  1. majority rule technique.

  2. nominal group technique.

  3. Delphi technique,

  4. idea/mind mapping technique.

Answer: B


QUESTION: 348

At which stage of team development do members begin to work together, adjust work habits, and trust each other?


  1. Forming

  2. Storming

  3. Norming

  4. Performing


Answer: C


QUESTION: 349

Which of the following can be used as an input for Define Scope?


  1. Product analysis

  2. Project charter

  3. Scope baseline

  4. Project scope statement


Answer: B


QUESTION: 350

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:


  1. Manage Stakeholder Expectations.

  2. Monitor and Control Risks.

  3. Plan Risk Management.

  4. Report Performance.


Answer: A


QUESTION: 351

Which of the following is a tool and technique used to monitor risk?


  1. Technical performance measurement

  2. Cost performance baseline

  3. Benchmarking

  4. Cost of quality


Answer: A


QUESTION: 352

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?


  1. Sensitivity analysis

  2. Three-point estimate

  3. Modeling and simulation

  4. Expected monetary value analysis


Answer: D


QUESTION: 353

Which of the following is an output of Close Procurements?


  1. Accepted deliverables

  2. Organizational process assets updates

  3. Managing stakeholder expectations

  4. Performance reports


Answer: B


QUESTION: 354

The probability and impact matrix is primarily used to:


  1. Quantify risk issues for trends during a quality audit.

  2. Develop a risk register for risk planning.

  3. Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

  4. Define risk and compare impacts during Perform Quantitative Risk Analysis.


Answer: C


User: Mohammed*****

I have renewed my subscription with Killexams.com for the PMI-100 exam because their exams and resources have been crucial to my success. I am confident that I can achieve my PMI-100 accreditation with their help and score above 95% on the exam.
User: Simeon*****

I am delighted to say that I passed my PMI-100 certification exam with a score of 97%! I was initially unsure about the accuracy of the exam material, but after practicing with the online test simulator and studying the content, I was pleased to have discovered Killexams.com. Thank you very much, Killexams.com, for helping me achieve my certification goals.
User: William*****

I am thrilled to have passed my PMI-100 exam with a nearly perfect score of 98% thanks to Killexams! The material in the package is accurate and valid, just like the questions on my actual exam. I was able to answer most of the questions easily, and some of the extra questions were very similar to the ones covered in the test guide, so I had no trouble answering them. This not only helped me expand my professional knowledge, but it also gave me a smooth path to my PMI-100 certification.
User: Valentino*****

Initially, I struggled to understand the complex topics while preparing for the pmi-100 exam using extensive study materials. However, a recommendation to try the practice tests from killexams.com proved to be a game-changer. Using their resources, I was able to quickly memorize the key information and confidently answer 67 questions in only 76 minutes, achieving an impressive 85% score. I am grateful to killexams.com for making my preparation so effective.
User: Mike*****

For a reliable PMI-100 practice test and the best training ever, killexams.com is the ultimate source of help. The exam simulator guided me through every aspect of the exam and provided the best questions and answers I have ever seen.

Features of iPass4sure PMI-100 Exam

  • Files: PDF / Test Engine
  • Premium Access
  • Online Test Engine
  • Instant download Access
  • Comprehensive Q&A
  • Success Rate
  • Real Questions
  • Updated Regularly
  • Portable Files
  • Unlimited Download
  • 100% Secured
  • Confidentiality: 100%
  • Success Guarantee: 100%
  • Any Hidden Cost: $0.00
  • Auto Recharge: No
  • Updates Intimation: by Email
  • Technical Support: Free
  • PDF Compatibility: Windows, Android, iOS, Linux
  • Test Engine Compatibility: Mac / Windows / Android / iOS / Linux

All PMI Exams

PMI Exams

Certification and Entry Test Exams

Complete exam list