Answer: B
QUESTION: 611
During which process would you obtain stakeholders' formal acceptance of the completed project scope?
Quality control
Scope verification
Scope control
Close project
Answer: B
QUESTION: 612
The initial development of a Project Scope Management plan uses which technique?
Alternatives identification
Scope decomposition
Expert judgment
Product analysis
Answer: C
QUESTION: 613
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
Risk register
Risk breakdown structure (RBS)
Risk management plan
Risk category
Answer: B
QUESTION: 614
Which is a tool or technique used in scope definition?
Templates, forms and standards
Change requests
Stakeholder analysis
Project assumptions
Answer: C
QUESTION: 615
What is the total float of the critical path?
Can be any number
Zero or positive
Zero or negative
Depends on the calendar
Answer: C
QUESTION: 616
Which of the following is the correct network diagram for the table?
Begin - A - C - D - E - End - B - D
Begin - A - B - C - D - E - End
Begin - A - B - D - E - End A - C - D
Begin - A - C - D - E - End - B - C
Answer: A
QUESTION: 617
Which of the following is a schedule network analysis technique that takes limited resources into account?
Network reserve analysis
Critical chain method
Lead and lag adjustment
Critical path method
Answer: B
QUESTION: 618
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
The risk of achieving the shortened project time is increased.
The critical path will have positive total float.
Contingency reserves are released for redeployment by the project manager.
Duration buffers are added to maintain a focus on planned activity durations.
Answer: A
QUESTION: 619
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
Analogous
Parametric
Bottom-up
Top-down
Answer: A
QUESTION: 620
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days. What should be your concern?
There is a cost under run.
There is a cost overrun.
May not meet deadline.
The project is 20 days behind schedule.
Answer: B
QUESTION: 621
Which illustrates the connection between work that needs to be done and its project team members?
Work breakdown structure
Network diagrams
Staffing management plan
Responsibility matrix
Answer: D
QUESTION: 622
When can pre-assignment of project team members occur?
When the project uses capital expenditures.
When the required staff can be acquired from outside sources.
When the project would be ignored due to travel expenses.
When the project is the result of specific people being promised as part of a competitive proposal.
Answer: D
QUESTION: 623
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
Risk identification
Qualitative risk analysis
Risk management planning
Quantitative risk analysis
Answer: B
QUESTION: 624
In which process might you use risk reassessment as a tool and technique?
Qualitative risk analysis
Risk monitoring and control
Monitor and control project work
Risk response planning
Answer: B
QUESTION: 625
A contract management plan is a subsidiary of what other type of plan?
Resource plan
Project management plan
Cost control plan
Expected monetary value plan
Answer: B
User: Elizabeth*****![]() ![]() ![]() ![]() ![]() I owe a debt of gratitude to Killexams.com for providing such high-quality exam practice tests. The iseb-pm1 exam practice tests were valid and helped me achieve a 95% score. I plan to return for additional test prep and highly recommend Killexams.com to anyone looking for comprehensive study materials. |
User: Daniela*****![]() ![]() ![]() ![]() ![]() Unmatched testprep guidance was pivotal in my passing the ISEB-PM1 exam with an extraordinary grade. Their teaching approach built my confidence, making success achievable, and I credit my professional growth to their outstanding resources. |
User: Okb*****![]() ![]() ![]() ![]() ![]() Questions closely matched the actual iseb-pm1 exam. After failing once, their Q&A and simulator helped me pass effortlessly. Their resources are a must-have. |
User: James*****![]() ![]() ![]() ![]() ![]() I purchased the online mock exam for the ISEB-PM1 exam and passed it on my very first attempt. I am so grateful for the help provided by Killexams.com. I scored 98%, which is a huge accomplishment for me. The Killexams.com team is wonderful, and I sincerely hope they continue to update their questions and maintain their excellent work. |
User: Thiago*****![]() ![]() ![]() ![]() ![]() I passed my iseb-pm1 exam with an 88% score, thanks to Killexams.com’s question bank. Their regularly updated database is a must-use for certification candidates. |
Features of iPass4sure ISEB-PM1 Exam
- Files: PDF / Test Engine
- Premium Access
- Online Test Engine
- Instant download Access
- Comprehensive Q&A
- Success Rate
- Real Questions
- Updated Regularly
- Portable Files
- Unlimited Download
- 100% Secured
- Confidentiality: 100%
- Success Guarantee: 100%
- Any Hidden Cost: $0.00
- Auto Recharge: No
- Updates Intimation: by Email
- Technical Support: Free
- PDF Compatibility: Windows, Android, iOS, Linux
- Test Engine Compatibility: Mac / Windows / Android / iOS / Linux
Premium PDF with 625 Q&A
Get Full VersionAll ISEB Exams
ISEB ExamsCertification and Entry Test Exams
Complete exam list